Construction and site works at Cooma North Shops Playground are now complete.
The playground has been handed over to SMRC Facilities and was opened to the public on Wednesday 13 March 2019.
Cooma North Shops Playground is another project delivered through the Stronger Communities Fund Major Projects Program (SCFMPP).
Official Opening Day Celebrations
Completion Photos
Progress Photos
Cooma North Shops Playground - Consultation Summary
Council would like to thank everyone who participated in providing valuable feedback for the Cooma North Shops Playground concept designs that will be delivered as part of the Stronger Communities Fund – Major Projects Program (SCFMPP).
The consultation period ran between 30 October 2018 and 16 November 2018. Please download the summary report here.
School 'Sneak Peak' - Tuesday 30 October 2018
The project team visited Cooma North Public School and Snowy Mountains Christian School on Tuesday 30 October 2018 with the students given the opportunity to review the designs before being released to the public. A real 'sneak peek' was offered to show large printouts of the layout and design of the new site and students could ask questions about the Cooma North Shops Playground or any of the playground projects being delivered.
Final Approved 3D Designs:
Construction and site works at Cooma North Shops Playground are now complete.
The playground has been handed over to SMRC Facilities and was opened to the public on Wednesday 13 March 2019.
Cooma North Shops Playground is another project delivered through the Stronger Communities Fund Major Projects Program (SCFMPP).
Official Opening Day Celebrations
Completion Photos
Progress Photos
Cooma North Shops Playground - Consultation Summary
Council would like to thank everyone who participated in providing valuable feedback for the Cooma North Shops Playground concept designs that will be delivered as part of the Stronger Communities Fund – Major Projects Program (SCFMPP).
The consultation period ran between 30 October 2018 and 16 November 2018. Please download the summary report here.
School 'Sneak Peak' - Tuesday 30 October 2018
The project team visited Cooma North Public School and Snowy Mountains Christian School on Tuesday 30 October 2018 with the students given the opportunity to review the designs before being released to the public. A real 'sneak peek' was offered to show large printouts of the layout and design of the new site and students could ask questions about the Cooma North Shops Playground or any of the playground projects being delivered.
Share Have 'Your Say' on the Cooma North Shops Playground design on FacebookShare Have 'Your Say' on the Cooma North Shops Playground design on TwitterShare Have 'Your Say' on the Cooma North Shops Playground design on LinkedinEmail Have 'Your Say' on the Cooma North Shops Playground design link
Cooma North Shops Playground has finished this stage
Community comment to review the playground concept designs will be open for 14 business working days.
Open: Tuesday 30 October 2018
Cooma North Public School: Tuesday 30 October 2018 at 11:00am
Snowy Mountains Christian School: Tuesday 30 October 2018 at 2:30pm
Close: Friday 16 November 2018
Community Consultation - Evaluation and Review
Cooma North Shops Playground has finished this stage
An evaluation and review of comments / feedback will commence immediately following community consultation.
Please see Consultation Summary report, when available.
Playground design approval
Cooma North Shops Playground has finished this stage
Following Community Consultation, Snowy Monaro Regional Council will work with the contractor to approve and finalise the concept designs to proceed to manufacture.
Manufacturing of Playground Equipment
Cooma North Shops Playground has finished this stage
December 2018 - January 2019
Site Works
Cooma North Shops Playground has finished this stage
February 2019
Playground Complete - Open Day
Cooma North Shops Playground is currently at this stage